Monday 16 June 2025 | | home |
![]() | archive |
| |
![]() ::: RMT ScotRail staff walk out |
![]() Railhub Archive | ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() RailtrackLetter from Gerald Corbett
25 April 2000 Mr T Winsor Rail Regulator Office of the Regulator I Waterhouse Square 138-142 Holborn LONDON EC I N 2TQ Dear Tom West Coast Main Line In respect of Annex Three of our representations and objections and the schedule to that Annex, I would draw your attention to Railtrack's request that they be treated as commercially sensitive information and that their contents be withheld from publication on the grounds that publication would seriously and prejudicially affect Railtrack's interests. In Annex Three you will also note Railtrack's acceptance that the information given to you to date regarding work which is unreasonable or uneconomic has not been detailed enough. The schedule to Annex Three goes some way towards remedying that omission. As Annex Three states, further information will be given to you on or by 5th May. Yours sincerely Gerald M N Corbett Representations and Objections to the Regulator's Modified Draft Final Order WEST COAST MAIN LINE A. Introduction 1. This document contains the representations and objections made by Railtrack PLC in accordance with s.56(4) of the Railways Act 1993 (the Act) to the Notice and modified draft final order (MDFO) published by the Rail Regulator (Regulator) on 27 March 2000. 2. Railtrack welcomed the meetings between the Office of the Rail Regulator (ORR) and Railtrack which were held to try and clarify issues arising from the 5 November 1999 draft final order (DFO), and the constructive approach adopted by the Regulator in seeking to accommodate Railtrack's concerns. Railtrack also welcomes the fact that some of the modifications to the DFO have met several of the concerns expressed in its Representations and Objections (Original Representations) of 14 December 1999. A number of other misunderstandings on both sides have also been resolved. 3. However, Railtrack remains of the view that a final order is unnecessary and that the statutory conditions for the making of an order are not satisfied (see sections 55(1) and 55(5)(b) of the Act). Railtrack is also concerned that the specification of some of the requirements set out in the MDFO still remain unclear, and that others cannot practically be achieved. 4. In addition, some of the requirements in the MDFO have already been completed. Without prejudice to Railtrack's general submission that the statutory conditions for the making of an order are not satisfied, those requirements could not be requisite for the purpose of securing compliance with Railtrack's Licence within the meaning of section 55(1) of the Act. 5. Following discussions with ORR, and based on Railtrack's understanding of the MDFO, Railtrack has produced a further Project Plan and a copy is attached to these representations and objections as Annex 1. In Railtrack's judgement the Project Plan represents the best achievable process and timescale for the delivery of the remaining requirements of the MDFO. 6. Railtrack urges the Regulator to reconsider this draft final order process, which has lasted for almost six months. Throughout that time Railtrack has continued the planning and implementation of the West Coast Main Line (WCML) project. It is in the nature of such projects that over time the detailed methods of implementation are developed and that customers' reasonable requirements become clearer, with the result that frequent changes to the project are made. Changes are inevitable, and yet the detailed timetabling, review and other requirements set out in the MDFO (and previously the DFO) seek to freeze the project at a particular moment in time, with the risk that nugatory work is required to be undertaken because the requirements are out of date. Railtrack understands the concerns expressed by the Regulator up to November last year, but it firmly believes that the WCML project is being properly managed. 7. Save as stated, Railtrack has no objection to these representations and objections being published on the ORR website. Railtrack intends to publish these representations and objections on its website. B. Railtrack's WCML project action since November 1999 8. As the Regulator is aware, Railtrack is continuing to devote significant resources to the WCML project, and has recently published the second issue of detailed route upgrade plans for each one-eighth mile section of track. More than £1.2 billion of expenditure has already been authorised, and more than £800 million of contracts are underway. 9. Throughout this enforcement order process Railtrack has pressed on with its Project Plan. Railtrack completed on schedule: · the freight routing strategy (issue 1) on 29 February; · the costed specifications for the freight routing strategy (issue 1) on 29 February; · phase 2 of the specimen timetable on 14 April; · phase 2 draft Rules of the Plan on 14 April; · phase 2 infrastructure specifications on 14 April; · the freight routing strategy (issue 2) on 20 April; and · the costed specifications for the freight routing strategy on 20 April. 10. Monthly reports on progress have been sent to ORR, as promised. A copy of the Project Plan followed to produce that and other work is attached to these representations and objections as Annex 2. Baseline 2 Costs and Joint Working Group 11. On 31 January 2000, following the Black Diamond day review, Railtrack submitted to the Regulator the Baseline 2 Cost Plan. About five weeks later ORR proposed the formation of a Joint Working Party to spend eight weeks intensively reviewing that cost plan, and then to discuss that review at a hearing on 11 May. ORR accepted that such a review would involve difficult and complex issues. Railtrack pointed out that if the review process took place key resources would have to be deployed in order to make the review worthwhile, and that this would have an effect on its ability to comply with its Project Plan. In the event the review started immediately. 12. As part of the review eight output options are being considered. Each of those options is being costed. In the time available it is only possible to make assumptions regarding the capacity that each option will provide. The Joint Steering Group (which oversees the Joint Working Group; ORR is represented on both groups) agreed that costed specifications would be prepared and that an option would be selected before timetabling work was carried out to confirm the capacity which the selected option could provide. This is because it would be impossible to complete the timetabling work in time for the review. In addition, until the preferred option is known, any timetabling work that is carried out is in danger of being nugatory. 13. The detailed timetabling requirements in the MDFO should be seen in that light. As explained below, Railtrack is concerned that a requirement to carry out timetabling requirements before the preferred option is known is unreasonable since it may result in nugatory work. WCML project progress 14. The Regulator visited the WCML project team on 26 January and was given a detailed briefing on the project plans and progress of the WCML project. Following that presentation the Regulator stated that he was impressed with the improvement in project planning and management. The many steps taken by Railtrack in the last year have also been recognised by West Coast Trains Limited (WCTL), whose Chief Executive has recently been reported in the press as stating that he now believes Railtrack can deliver in time. In giving these examples Railtrack does not seek to argue that the WCML project is no longer free from problems. Given the size and complexity of the project, that could hardly be the case. However, the WCML project is being properly managed, and the enforcement order process is unnecessary. C. The modified draft final order: General 15. In paragraph 2.4.3 of the notice the Regulator states that: "since late December 1999 ORR has striven to identify the changes which could be made to the draft order which would meet Railtrack's concerns about the practicability of doing the work required by the draft order, whilst ensuring that the Regulator, train operators and funders received timely information they could use". 16. Despite the fact that it served its Original Representations on 14 December 1999, Railtrack received no reaction from ORR to those representations until the meeting held on 19 January; a period of five weeks. That meeting was held only so that ORR could clarify a few points regarding the Original Representations. Further, at that meeting ORR said that within two weeks some indication would be given as to how ORR intended to proceed: either to seek undertakings or to propose an amended order. In fact, no such indication was given. At the meeting ORR also clearly stated that it was in no one's interests for an order to be made which Railtrack could not meet. Unfortunately, despite further meetings, the MDFO does contain requirements which Railtrack is unable to meet. 17. It should be noted that by the time of the 19 January meeting, work in accordance with the Project Plan was already well underway. Approximately two thirds of the freight strategy review had been completed. Over 40% of the 2005 specimen timetable had been prepared, and approximately 30% of the work required for the strategic reviews had taken place. This demonstrates the difficulties involved in applying an enforcement order process to such a complex project over a lengthy period of time. 18. Railtrack believes that the five weeks it took for ORR to consider the Original Representations is an indication of the complex interaction of the issues that are involved. This is especially the case when the enforcement order process attempts to 'freeze' the continuing project process at a particular moment in time. The longer the enforcement order process lasts the more difficult and complicated that attempt becomes, because the evolving aspects of the project have to be addressed in the draft order, which may then be out of date as Railtrack will have already taken further steps in respect of the Project Plan, and the proposed requirements in the DFO and MDFO. That it took over three months from receipt of the Original Representations to publication of the Regulator's proposals regarding a modified order supports this view. Dwell Times 19. One such issue relates to dwell times (the time a train is at rest at a station). ORR was advised in December 1999 that as required by the DFO Railtrack proposed to include in its timetables the dwell times specified in its track access agreement with WCTL. ORR now maintains that if Railtrack feels that the dwell times are unrealistic, they should not be included in the timetabling work. ORR contends that Railtrack should use its best judgement to determine which dwell times should be included. In ORR's view this would result in a realistic timetable, on which train operators may with confidence rely. ORR is aware that WCTL has been asked for information regarding likely dwell times, but that WCTL has said that its review is not yet complete. 20. On 19 January, as promised in its Project Plan, Railtrack held a consultation meeting with representatives of TOCs, FOCs, sSRA and the Regulator. At that meeting Railtrack circulated draft Rules of the Plan, which included the contractual dwell times which would be used when preparing the phase 2 specimen timetable. Railtrack has yet to receive any substantive comments on the draft Rules of the Plan from any of those who attended that meeting. It would be helpful if TOCs and others were to respond to Railtrack in a timely fashion with their views. 21. Railtrack will use its judgement to estimate the likely WCTL dwell times, because the Regulator has insisted that such an approach be taken. However, because of the complex interaction of the issues, a change in the dwell times will necessarily involve changes in assumptions about other factors, such as stopping patterns and required infrastructure. Train operators will therefore not be able to rely with confidence on the specimen timetable until WCTL has confirmed its requirements. If WCTL then gives dwell times which differ from those assumed by Railtrack, the timetabling work will have been nugatory and will have to start again. Minutes 22. Because of the complexity of the issues contained in the DFO, and the scope for misunderstanding, Railtrack provided minutes of meetings to ORR so that they could be discussed and agreed. That process was followed in respect of a meeting on 28 January but on 11 February ORR informed Railtrack that it was not prepared to agree minutes, citing the fact that Railtrack was seeking legal advice. In response (on 14 February) Railtrack made it clear that: "in seeking to record the points which we discussed or agreed, I am simply trying to follow the proper process. Both Railtrack's and ORR's actions may be reviewed at some stage. However, far more important is the need to reduce misunderstandings and ambiguity. The meeting we had on 09 February was necessary because mutual misunderstandings arose on 28 January. These meetings have been useful in identifying and resolving some of the misunderstandings which have occurred, and in my view it is essential and useful in agreeing a record of what we agreed ...." 23. It is regrettable that it has not been possible to agree the content of any further minutes. A number of meetings and telephone conversations have taken place between ORR and Railtrack. As it is, a number of misunderstandings have remained. These are discussed in Section D. D. Specific requirements of the modified draft final order Paragraph 1(a): Production of Freight Routing Strategy 24. As worded, this obligation still involves the analysis of 18 periods of time from 1 May 2000 to 1 May 2009, based on two timetable changes per year. In paragraph 5.2 of its Original Representations Railtrack explained this point and stated that in the time available such an amount of work would not be practicable. During a meeting on 16 March ORR appeared to understand the problem, and said the issue would be clarified in any future final order. In paragraph 3.3.4 of the Notice dated 27 March the Regulator said: "The Regulator accepts the assumptions in paragraphs 5.0, 5.2 and 5.4, and has modified the draft final order accordingly” (emphasis added) 25. However, the Regulator has not modified the draft final order accordingly. The relevant wording is the same as in the DFO. Railtrack must therefore object to paragraph 1(a) in its present form, since the work is impossible to achieve in the time allowed. 26. As discussed during meetings with ORR, Railtrack has proceeded with the production of one freight routing strategy, which was provided to ORR on 20 April. If, therefore, the draft final order had been modified, Railtrack would now have satisfied the requirement, and paragraph 1(a) would not be requisite for the purpose of securing compliance with Railtrack's Licence condition. Paragraph 1(b): Freight Routing Strategy: costed specifications 27. The MDFO requires the costed specifications to be provided on or before seven days after the making of the MDFO. 28. On 16 March Railtrack confirmed that as a result of the need to devote resources to the joint review of costs (see paragraph 11 above) the planned date for the production of the costed specifications had moved to 20 April. That date was met, and Railtrack has provided the costed specifications. Railtrack has therefore satisfied this requirement and paragraph 1(b) is not requisite for the purpose of securing compliance with Railtrack's Licence condition. Paragraph 1(c)(i): Specimen Timetable 29. In paragraph 2.4.15 of Chapter 2 of the Notice dated 27 March the Regulator has noted Railtrack's statement that if the relevant timetabling work had to start afresh, it would not be possible to achieve the 15 May deadline; but that Railtrack had agreed to consider the basis on which it could complete the timetabling work either in draft or final form by that deadline. 30. Railtrack agreed to do so during the meeting with ORR held on 16 March. At that meeting Railtrack suggested producing a "rough cut" of the proposed timetable by 15 May, and completing that timetable by 24 July. 31. Railtrack remains able by 22 May (the date now specified in the MDFO) to produce a ‘rough cut’ draft timetable with reduced geographical scope (Euston to Crewe, Crewe to Manchester, Rugby to Birmingham New Street) for all trains providing for all movements on a 24 hour basis, but not validated. The rough cut timetable will not provide a statement explaining how in Railtrack's view the timetable provides a standard of operational performance which meets the reasonable requirements of train operators and funders. 32. By 24 July Railtrack will be able to produce a final version of the same specimen timetable which will cover and include: · the geographic scope specified in the MDFO; · draft Rules of the Plan; · full timetable validation; and · the statement referred to in paragraph 31 above. 33. It is not possible to produce a final version of the timetable by the date specified in the MDFO. In addition, the MDFO does not distinguish in substance or in time between a ‘rough cut’ timetable, and a final version of the same timetable. As a consequence, and as explained to ORR on 16 March, Railtrack is unable to comply with this paragraph as it is presently worded. If therefore the Regulator proceeds with the modified final order it will be necessary to extend the completion date, or to modify the MDFO to require the timetable described in paragraph 31. If that does not happen the Regulator will be making an order which he knows (and knew before the MDFO was issued) that Railtrack would be unable to comply with. Paragraph 1(c)(ii): Draft Rules of the Plan 34. Consistent with its position as regards paragraph 1(c)(i), Railtrack will be able to produce interim draft Rules of the Plan by 22 May. By 24 July Railtrack will be able to produce revised draft Rules of the Plan which it considers would be necessary to propose in accordance with the Railtrack Track Access Conditions to enable the specimen timetable to be operated to produce the capacity referred to in paragraph 1(c)(i). Those Rules of the Plan do not contain a statement regarding "the assumptions and allowances for performance made by Railtrack" (see paragraph 53 below). Paragraph 1(c)(iii): Statement of Capacity Difference 35. Railtrack welcomes this modification to the MDFO and assumes it was made because it takes up to three months to produce a timetable. However, the details required in such a statement (which term is not defined) are not clear. The preparation of a statement would presumably have to: · analyse the component parts of the timetable produced under 1(c)(i); · analyse, using the same methodology, the component parts of the modified "capacity commitments", as defined; and · identify and state the difference between the two. 36. A statement might include the following information for each train path or group of train paths: origins and destinations, number of trains per day (in each direction); stopping patterns; first and last trains; tolerance on intervals; dwell times; turnaround times; journey times; and timing load. 37. However, Railtrack does not know whether the requirement that a statement is produced would be met by the provision of such information. Railtrack must therefore object to this part of the MDFO. 38. It would not be possible to produce a ‘rough cut’ statement by 22 May, because there would be insufficient information available by that date. Assuming that the information referred to in paragraph 36 is broadly what is required, Railtrack would be able to produce a statement by 24 July. (This assumption also holds good in respect of paragraphs 1(c)(iv) and (v), discussed below). Paragraph 1(c)(iv) 39. For the same reasons as stated in paragraph 38 above, Railtrack is not able to produce the statement required in paragraph 1(c)(iv) until 24 July 2000. Paragraph 1(c)(v) 40. Railtrack is able to produce the statement required in paragraph 1(c)(v) on or by 24 July 2000. Paragraph 1(d): Strategic Reviews 41. Railtrack will endeavour to provide strategic reviews by 22 May 2000 (although Railtrack's Project Plan specified 31 May), subject to the following issue. 42. During a meeting on 04 April ORR asked Railtrack to explain what assumptions it intended to make with regard to the base for the strategic reviews. Railtrack stated that the basis was the infrastructure comprising the Specified Works, as defined in the MDFO (although see paragraph 44 below). In response, ORR stated that in complying with this part of the MDFO Railtrack should also have regard to paragraph 3.3.21 of the Notice dated 27 March. By this ORR apparently meant that in order to comply with paragraph 1(d), Railtrack had to use as one of its assumptions not only that the infrastructure should be the Specified Works, but that it should also include as a base the infrastructure required for the PUG 2 contractual commitments and Railtrack's undertakings. Railtrack believes that it would be unreasonable and unrealistic to produce strategy reviews with those assumptions as a base. It is unreasonable because: · the timetabling assumptions accepted by the Regulator are based on the Specified Works and not on an infrastructure specification which would meet the capacity commitments in full. It would be unreasonable to produce strategic reviews under a different assumption; and · the Joint Review has always assumed that Option 7 (see paragraph 12 above) provides the maximum infrastructure to be built. It would be inconsistent to produce a strategic review based on anything greater. 43. In any event, if it was necessary to produce strategic reviews using the assumptions the Regulator requires, Railtrack would first have to complete the work contemplated in paragraph 1(c). Since the statements and the review are both required by 22 May, it follows that the statements would have to be produced well before 22 May. That timescale is not possible. 44. Railtrack notes that the Regulator's definition of Specified Works refers to the 'Functional Specification....(Issue Formal 2)'. Railtrack issued a new functional specification on 10 March, which was sent to ORR and others shortly afterwards. Railtrack believes that the latest version (Formal 2.3) should be the basis for the work, save for the exceptions referred to in Railtrack's letter to ORR dated 21 March. Railtrack could work to the specification referred to in the MDFO but it would be unrealistic to do so. This is an example of the point made in paragraph 6 above: as time moves on the project progresses, and the risk increases that necessary changes are not all reflected in the enforcement process. Any final order should refer to the current functional specification. Paragraph 1(e): Identity of risk assessor 45. As the Regulator is aware, the identity and address of the independent risk assessor has already been notified to him. This part of the MDFO is therefore not requisite for the purposes of securing compliance with Railtrack's Licence condition. Paragraph 1(f): Unqualified certificate 46. Railtrack notes this part of the MDFO. A certificate in respect of the costed specifications required under paragraph 1(b) of the MDFO has already been provided to the Regulator. Paragraph 2(1): Modification treated as agreed 47. Railtrack notes this part of the MDFO. Paragraph 2(2): Use of stated requirements of operator 48. Railtrack notes this part of the MDFO.Paragraph 2(3): Statement accompanying timetable 49. At the meeting with ORR held on 16 March it was accepted that a statement explaining how a timetable provides for a standard of operational performance had never been prepared before, whether by Railtrack or its predecessors. There are therefore no accepted methods or standards to follow. Railtrack has also raised this point with TOCs and FOCs, and asked for views as to what such a statement should contain. No responses have been received. It would be unreasonable for an order to require a statement before there is any agreement about what such a statement should contain. It would be more realistic to agree the content of such a statement before the imposition of an order. Railtrack welcomes ORR's agreement, given on 16 March, to discuss this further. Paragraph 3: Publication of information 50. Railtrack notes this part of the MDFO. Since May 1999 it has been Railtrack's standard practice to publish widely timetables and strategic reviews (including the freight routing strategy). However, Railtrack has found that despite publication, it is rare to receive feedback from TOCs, FOCs and others. Paragraph 4(a): Provision of information to assessor 51. Railtrack notes this part of the MDFO. The independent risk assessor has been informed in writing that as soon as he requires information to enable him to give the required certification, he should ask for it. To the extent that the independent assessor makes known his requirements, Railtrack will timeously satisfy them. Paragraph 4(b): Contract of appointment of assessor 52. A copy of the contract was sent to ORR on 30 March. This part of the order is therefore not requisite for the purposes of securing compliance with Railtrack's Licence condition. Definitions Railtrack believes that the following definitions require clarification: 'Rules of the Plan' 53. Rules of the Plan produced in accordance with "the Railtrack Track Access Conditions" do not contain an explicit statement regarding "the assumptions and allowances for performance made by Railtrack". This definition and paragraph 1(c)(ii) of the MDFO are therefore inconsistent. 'Specified Works' 54. Railtrack has already noted (see paragraph 44) that the functional specification referred to in this definition is now out of date. Further changes will be made to the current functional specification as the WCML project develops. 'Specimen Timetable' 55. Railtrack notes this definition but draws the Regulator's attention to the phrase ‘'and demonstrating in all cases that services which do not run on each weekday can be accommodated on the days on which they run’. Railtrack understood that the definition of ‘Specimen Timetable’ had been modified to avoid the need to produce five timetables. For the avoidance of doubt, Railtrack understands that this requirement would be satisfied by the provision of one typical timetable, and a statement demonstrating how that timetable would vary to accommodate trains which do not run on each weekday. 56. Further, a standard hour timetable is required for all off peak hours for certain route sections. Railtrack needs to know whether the timetabling work should cover all trains arriving and departing during off peak hours. If so, because of the length of the sections in question, the timetabling work will have to extend beyond off peak hours. E. The Content of a Final Order 57. In its Original Representations Railtrack stated its belief that if the Regulator nevertheless made a final order, it should differ from the DFO so that the requirements were clear; the timescales practicable; the technological solutions feasible and that it should relate to economically practicable infrastructure which reflects train operators' and funders' reasonable requirements. In support of its belief Railtrack referred to the requirements of reasonableness, certainty, and compatibility with the principles of The European Convention on Human Rights. 58. Railtrack repeats these submissions, including that concerning the European Convention on Human Rights and submits that the making of an order in the terms of the MDFO would not be compatible with those principles. F. Railtrack's decision not to consent to the modifications 59. Railtrack's reasons for deciding not to consent to the modifications proposed by the Regulator on 10 March can be summarised as follows. First, Railtrack did not accept that the statutory conditions for the making of a final order were satisfied. In particular, Railtrack did not accept that an order had to be made in order to secure compliance with its Network Licence. Railtrack continues to believe that the imposition of a final order is unnecessary. Second, Railtrack has a duty to minimise its exposure to any civil liability. Last, Railtrack was of the view that parts of the proposed order were unclear or not practicable. In Railtrack's view those reasons remain applicable to the MDFO. Consequences of not consenting to the modifications 60. During the meeting with ORR on 22 March, Railtrack made the point that: · if it consented to the modifications, then the information specified in the modified draft final order would have to be provided by the stated dates; whereas · if it did not consent to the modifications, and after considering any representations and objections the Regulator proceeded to make the modified draft final order without further modifications, then the same information would have to be supplied, by the same dates. 61. With those circumstances in mind, Railtrack said it would be helpful if ORR could explain why it was in Railtrack's interests to consent to the modifications. ORR responded by saying that if Railtrack consented to the modifications, better public relations would ensue. It is a matter of regret that the exercise of quasi judicial enforcement powers which expose Railtrack to the risk of civil liability is apparently linked to the issue of public relations.
Railhub Archive ::: 2000-04-25 RTK-001 | ![]() ![]() Monday![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() 14 stories ![]() ![]()
![]()
![]()
![]() |