Railhub Archive 2012-05-18 GBR-001 GB Railfreight0
GB Railfreight moves first Crossrail train
keywords: click to search
 Crossrail
 GB Railfreight
 GBRf
 Northfleet
 
Phrases in [single square brackets] are hyperlinks in the original document
Phrases in [[double square brackets]] are editorial additions or corrections
Phrases in [[[triple square brackets]]] indicate embedded images or graphics in the original document. (These are not usually archived unless they contain significant additional information.) | | 
         GB Railfreight moves first Crossrail train _______________________________________________________________
 type Press release
GBRf has transported the first trainload of excavated material from Crossrail’s tunnels in west London to Northfleet in Kent.
The train, comprising 13 wagons, carried 492 tonnes of earth to the Lafarge site at Northfleet. It is the first laden train to operate between the two sites for nearly two decades and was made possible after Lafarge reinstated a 2.25km disused rail freight link from the North Kent Main Line.
Over the next month or so, two trains per week will run a return journey between the Crossrail tunnel entrance near Paddington and Northfleet. Later in the summer, the trains will double in size and run three times a day.
At the peak of tunnelling up to five freight trains per day will operate, carrying a total of 7,000 tonnes of earth and – in conjunction with boat-based removals – removing at least 50,000 lorry journeys from central London.