Unplanned disruption to rail users, December 2014


keywords: click to search


Network Rail
Office of Rail Regulation
ORR
maintenance
renewals



Phrases in [single square brackets] are hyperlinks in the original document

Phrases in [[double square brackets]] are editorial additions or corrections

Phrases in [[[triple square brackets]]] indicate embedded images or graphics in the original document. (These are not usually archived unless they contain significant additional information.)


Office of Rail Regulation

Unplanned disruption to rail users, December 2014
_______________________________________________________________


related documents


2014-12-16 Network Rail's CP5 delivery and issues for CP6 (Office of Rail Regulation)

2014-12-27 DfT statements on rail disruptions and winter weather (Department for Transport)

2014-12-29 Media statement from Network Rail (Network Rail)

_______________________________________________________________


date
29 December 2014
source Office of Rail Regulation
type Letter



One Kemble Street
London, WC2B 4AN
020 7282 2000

Tara House, 46 Bath Street
Glasgow, G2 1HG

www.rail-reg.gov.uk

29 December 2014

Clare Moriarty,
Director General, Rail Executive
Department for Transport
Great Minster House,
London SW1P 4DR

Dear Clare,

UNPLANNED DISRUPTION TO RAIL USERS, DECEMBER 2014

The major investment programme Network Rail is undertaking to improve the
network in this control period means that substantial engineering projects
affecting the operational railway will be a common feature of the next five years,
so it is vital that the industry as a whole gets the management of this work right.

Following the disruption to passengers over the weekend on the routes from
King’s Cross and Paddington, we will be investigating (a) whether to take any
further regulatory action, and (b) to establish any lessons that need to be
learned for the industry. ORR will investigate specifically in relation to potential
licence breaches by the railway businesses involved.

Our role in investigating the disruption and its effects is defined in law and in
relation to the companies’ licences and is guided by the public interest, in
particular the interests of both present and future rail users. Our investigation
will look at three broad areas:

- Network Rail’s planning of engineering works;
- the provision of passenger information both by Network Rail and the relevant
train operators; and
- impacts on train service punctuality and reliability.

In addition we will be considering the management of safety using our powers
under health and safety law. ORR’s safety inspectors will also provide support
and evidence to our wider investigation and, where there are lessons from this
work which we can sensibly include in our broader findings we will do so.

We want to make sure the review has the right focus to get results so that the
industry can make sure there is no repetition of avoidable problems, and that
passengers are properly informed and protected when things do not go to plan.

With this in mind we will produce draft terms of reference for the review in the
next few days and will seek comments from passenger groups, the industry and
funders before they are finalised by the ORR Board. We will publish both draft
and final terms of reference. The investigation will cover the incidents affecting
King’s Cross and Paddington, but we will include any other instances of
significant disruption affecting passengers elsewhere on the network that come
to our attention.

We are aware that Network Rail is undertaking its own reviews on the causes of
these incidents and more broadly on the planning and timing of engineering
work, and we will make sure we co-ordinate with them to ensure we have a
consistent information base. We will look at findings of previous reviews of the
management of projects and their consequences for passengers, including work
by the industry and recent relevant inquiries on passenger information during
disruption.

The investigation will be led by Joanna Whittington, one of my Directors.
Joanna will be supported by the appropriate ORR experts and two of our non
executive directors will provide support, challenge and relevant expertise to the
investigation. We will also work closely with Passenger Focus and other
relevant passenger groups to make sure that passengers’ views are
represented and understood, and with others who were involved including the
train operators, London Underground and the British Transport Police.

We aim to complete the investigation by the end of January so that we can
report to the Board both on what caused the problems and on what further
action is required in the light of our regulatory role. We will, of course, publish
our report.

I am copying this letter to Mark Carne at Network Rail, Louise Ellman MP, Chair
of the Transport Select Committee; Michael Roberts at the RDG; Michael
Holden at Directly Operated Railways; David Brown at Go-Ahead; Chris
Burchell at Arriva; Tim O’Toole at First Group; Keith Greenfield at Heathrow
Express; Anthony Smith at Passenger Focus; Mike Brown at London
Underground and Paul Crowther at the British Transport Police. I am also
putting a copy on ORR’s website.

With best wishes,
RICHARD PRICE
Chief Executive