::: RMT threatens national industrial action over service cuts



Railhub Archive
2015-06-25 NET-002
Network Rail

0

Network Rail confirms review of five-year CP5 plan


keywords: click to search


railway costs



Phrases in [single square brackets] are hyperlinks in the original document

Phrases in [[double square brackets]] are editorial additions or corrections

Phrases in [[[triple square brackets]]] indicate embedded images or graphics in the original document. (These are not usually archived unless they contain significant additional information.)


Network Rail

Network Rail confirms review of five-year CP5 plan
_______________________________________________________________


related documents


Network Rail annual report 2015

2015-06-25 Network Rail chairman to step down (Network Rail)

2015-06-25 Network Rail’s performance (Department for Transport)

2015-06-25 New Chair of Network Rail announced (Department for Transport)

_______________________________________________________________


date
25 June 2015
source Network Rail
type Press release



National

More train passengers arrived at their destination on time last year than ever before, Network Rail’s Annual Report has revealed today. Following decades of underinvestment, Britain is now investing record amounts in our railway to ensure it remains fit for purpose as well as able to accommodate the record number of trains. Britain now has the safest passenger network in Europe and the railway asset reliability is the best it has ever been, even whilst passenger numbers have doubled in the last 20 years.

However, Network Rail faces some stretching targets in Control Period 5 (CP5, 2014-19) and the pace of improvement is behind expectations. Several regulatory targets were missed and following slippages in the major projects portfolio, chief executive Mark Carne has given a frank assessment to the Department of Transport of what will be achievable in the remaining four years.

Mark Carne said: “During my first year in the job I have looked closely at every aspect of our business and it has become clear that Network Rail signed up to highly ambitious five-year targets set by the regulator. Based on historic improvements from a low base, we were overly optimistic about the capacity of our company and our supplier base to step up several gears in order to achieve the plan, especially given the complexities of a network that is at full capacity much of the time."

On the big items like electrification and capital projects, it was always part of the regulatory process that the costs and programme would be revisited as projects became properly defined. Unfortunately when these reviews have occurred, the more detailed project costs have been higher than assumed at the earliest stages of definition. As a result, the total enhancement programme cost now exceeds the available five-year budget. Some projects are also delayed beyond the original dates.

Mark Carne added “I recognise that these delays will cause disappointment for some passengers for which I can only apologise. I welcome the fact that the Transport Secretary has asked Sir Peter Hendy to work with me and my team to develop proposals for re-planning the programme over the next few months.”

Since joining last year, Mark Carne has brought in a largely new leadership team to drive the pace of change needed to build a better, more modern railway. The team has focussed particularly on devolving the company into eight regional businesses. This structure empowers route managing directors to quickly respond to the needs of their local passengers and train companies whilst enabling the company to benchmark performance and drive innovation and best practice much more transparently. It also deploys national services and systems to drive economies of scale and common standards, thus delivering better value for taxpayers.

Given the change in outlook compared to the regulatory settlement, Network Rail's remuneration committee has decided that no bonuses should be paid to its executive directors for 2014/15. Their bonus entitlement had already been reduced from a maximum of 160% of salary to 20% shortly after Mark Carne joined as chief executive last year. Mr Carne has previously announced that he would forego this year’s bonus.

ENDS

Notes to editors:

Network Rail achievements in 2014/15:

o Replaced over 600km of track and almost 300 junctions
o Finished the transformation of Reading station and its approaches a year early and under budget, eliminating the biggest bottleneck on the main line to London Paddington
o Completed 27 miles of electrification in the north west of England
o All but completed the building of Britain's first new domestic railway for over 100 years with 30 miles of new railway, including seven new stations, built in the Scottish Borders
o Transformed stations across the country such as Edinburgh Haymarket and Nottingham, with the redeveloped Birmingham New Street close to opening
o Secured the future of the Chiltern main line between Marylebone and Birmingham following the 350,000 tonne landslip at Harbury, near Leamington Spa
o Invested over £6bn in projects that sustained over 90,000 full time jobs
o Seen 99% of our expenditure made through UK-based companies, with almost 40% in small and medium sized businesses
o Completed over 90,000 small, medium and large schemes, with over 98% completed early or on-time

Contact information

Media Relations (National)
020 3356 8700
mediarelations@networkrail.co.uk


Railhub Archive ::: 2015-06-25 NET-002





Wednesday
20




Not logged on
Visitor










499 stories



2 documents



32 collections





6 documents



7 documents