Thursday 18 August 2022

 

< back | business | images | knowledge | library | rail unveiled | home


archive


::: Test message -_— £ $ ‘’



Railhub Archive
2020-09-25 DfT-001
Department for Transport

0

First phase of Dawlish seawall completed, securing South West’s rail links


keywords: click to search
Dawlish
resilience
weather



Phrases in [single square brackets] are hyperlinks in the original document

Phrases in [[double square brackets]] are editorial additions or corrections

Phrases in [[[triple square brackets]]] indicate embedded images or graphics in the original document. (These are not usually archived unless they contain significant additional information.)


Department for Transport

First phase of Dawlish seawall completed, securing South West’s rail links
_______________________________________________________________


related documents


Resilience of rail infrastructure. Interim report …(pdf)

_______________________________________________________________


date
25 September 2020
source Department for Transport
type Press release



New seawall at Dawlish reaches an important milestone.

o first phase of new seawall at Dawlish completed, protecting Isambard Kingdom Brunel’s historic rail route in the South West
o milestone moment forms part of government’s £80 million investment to improve resilience of railway following severe storms in 2014
o Rail Minister Chris Heaton-Harris visits new £25 million structure, preserving panoramic views for pedestrians and passengers, and an upgraded depot in Exeter

The completion of the first phase of a new seawall at Dawlish ensures an integral rail link for passengers and business across the South West is protected for “generations to come”, Rail Minister Chris Heaton-Harris announced today (25 September 2020).

Visiting the site to officially open the new £25 million structure on the seafront west of Dawlish station, the minister saw the first phase of the £80 million scheme designed to create a more resilient railway at an exposed location, which was severely damaged in storms in 2014.

The new structure – which runs from Colonnade underpass, west of Dawlish station, to Boat Cove – will protect 360 metres of railway and homes behind it. Constructed after detailed consultation with the local community, the design is focused on preserving the panoramic views and access to the coast for residents and tourists, as well as ensuring passengers and businesses can rely on a secure, reliable service.

The Rail Minister also visited a train maintenance depot at Exeter, which has been expanded in partnership with Network Rail and train operator GWR to accommodate an increase in its fleet size in the Devon and Cornwall area.

The £53 million upgrade helps deliver more seats on more frequent services for passengers, improving service reliability and capacity for passengers across the region.

Rail Minister Chris Heaton-Harris said:

Our investment in this new seawall will provide a resilient railway for generations to come, delivering for the thousands of passengers that rely upon this vital link every day, and the residents whose homes and businesses must be protected.

This rigorous set of defences forms part of our ambitious plans to deliver reliable, punctual journeys across Devon and Cornwall, improving connections between communities to help the South West build back better, boosting the local economy and tourism.

Network Rail’s plans for the second phase of the seawall, which extend it for a further 415 metres eastwards from Colonnades to Coastguards breakwater and include accessibility improvements to Dawlish station, have now been approved and work is expected to start next month, taking around 2 years to complete.

Rail media enquiries
Media enquiries
020 7944 3021

Out of hours media enquiries
020 7944 4292

Switchboard
0300 330 3000


Railhub Archive ::: 2020-09-25 DfT-001





Thursday
18




Not logged on
Visitor










13 stories